1175.12 MAINTENANCE AND FINAL INSPECTION APPROVAL.
      To receive final inspection and acceptance of any project, or portion thereof, the following must be completed and provided to the City of Aurora Engineer:
      (a)    Final stabilization must be achieved and all permanent SCMs must be installed and made functional, as determined by the City of Aurora Engineer, and per the approved Comprehensive Storm Water Management Plan.
      (b)    An As-Built Certification, including a survey and inspection, must be sealed, signed and dated by a Professional Engineer and a Professional Surveyor with a statement certifying that the SCMs, as designed and installed, meet the requirements of the Comprehensive Storm Water Management Plan approved by the City of Aurora Engineer. In evaluating this certification, the City of Aurora Engineer may require the submission of a new set of SCM calculations if he/she determines that the design was altered significantly from the approved Comprehensive Storm Water Management Plan. The As-Built Survey must provide the location, dimensions, and bearing of such SCMs and include the entity responsible for long-term maintenance as detailed in the Inspection and Maintenance Agreement.
      (c)    A copy of the complete and recorded Inspection and Maintenance Plan and Inspection and Maintenance Agreement as specified in Section 1175.08 must be provided to the City of Aurora Engineer.
      (Ord. 2022-080. Passed 5-23-22.)