§ 1232.02 APPLICATION AND SUBMISSION PROCESS.
   (a)   Submittal and review shall be in accordance with the following table of stages:
 
TABLE 1
Review Stage
Minor Subdivision
Major Subdivision
Land Development
Sketch
Optional
Recommended
Recommended
Preliminary
Recommended
Mandatory
Mandatory
Final
Mandatory
Mandatory
Mandatory
 
   (b)   Each presentation of a sketch, preliminary or final plan shall be considered a separate submission, and the application and review process will be the same for each submission.
   (c)   For all review stages where review and report are required or requested, nine copies of every subdivision or land development plan shall be submitted to the Township Secretary along with the township subdivision and land development application and fee, the township escrow fee for professional review of the plan and/or application, and the County Planning Department application and fee.
   (d)   The nine copies of plans shall be distributed to the following for review and report:
      (1)   Township Engineer, one copy;
      (2)   Building Inspector, one copy;
      (3)   Township file, one copy;
      (4)   Township Planning Commission, three copies; and
      (5)   County Planning Department, three copies.
   (e)   Review stages where review and report are required or requested shall be acted upon by the Board of Commissioners and a decision rendered and communicated not later than 90 days following the date of the regular meeting of the Board, or otherwise following the date the application is filed, provided that should the next regular meeting occur more than 30 days following the filing of the application, the said 90-day period shall be measured from the thirtieth day following the date the application was filed.
   (f)   The decision of the Board shall be communicated in writing to the applicant personally or mailed to him or her at his or her last known address not later than 15 days following the decision.
(Ord. 668, passed 10-17-1990)