§ 818.16 TIME LIMIT FOR INSTALLATION OF SYSTEM.
   Installation of the system shall be commenced within 90 days after the franchise is granted by the township. Mapping of the township is to be considered commencement of the installation. Significant construction shall be accomplished within one year after Federal Communications Commission authorization and energized trunk cable shall be extended to at least 20% of the franchise area each subsequent year, with completion of construction to be accomplished within five years of the issuance of FCC certification.
(Ord. 474, passed 9-20-1978)