§ 52.39 AS-BUILT DRAWING REQUIREMENTS.
   (A)   Prior to the final release of any bonds or other fiscal security that may be required for new developments or redevelopment projects or prior to the issuance of a certificate of occupancy, the project developer and/or contractor shall submit to Public Works Department as-builts of the newly constructed site improvements and storm water facilities.
   (B)   The as-built condition of these storm water facilities and other site improvements shall be certified by a Professional Engineer and must be reviewed and approved by the Public Works Department. As-builts shall be provided in both paper copy and electronic format, in a version acceptable to Public Works Department.
(Ord. 64-2010, passed 6-24-10)