(A) Prior to the final release of any bonds or other fiscal security that may be required for new developments or redevelopment projects or prior to the issuance of a certificate of occupancy, the project developer and/or contractor shall submit to Public Works Department as-builts of the newly constructed site improvements and storm water facilities.
(B) The as-built condition of these storm water facilities and other site improvements shall be certified by a Professional Engineer and must be reviewed and approved by the Public Works Department. As-builts shall be provided in both paper copy and electronic format, in a version acceptable to Public Works Department.
(Ord. 64-2010, passed 6-24-10)