(A) The review timeline does not apply to planned area developments.
(B) The city shall issue an applicant a written or electronic notice of administrative completeness or deficiencies within 30 calendar days.
(C) If the city fails to issue the notice with 30 calendar days, the application shall be considered administratively complete.
(D) Resubmittals will be determined for administrative completeness within 15 calendar days after receiving the requested documents.
(E) When the application is administratively complete, the city shall approve or deny it within 180 calendar days.
(F) Extension. The city may allow an extension beyond 180 calendar days for the following reasons:
(1) The city may have a one-time extension of no more than 30 calendar days for extenuating circumstances.
(2) If the applicant requests an extension, the city may grant extensions in 30 calendar day intervals.
(Ord. 1557, passed 11-19-2024)