(A) This chapter contains information to assist the consultant in the preparation of all construction plans and documents to be submitted to the city for approval.
(B) All plans shall conform to the latest revised copy of the city’s Engineering Standards (this Chapter) and Apache Junction Standard Details set forth in Apache Junction City Code Vol. II, Appendix 10-D to this Chapter.
(C) Any deviation from this Chapter requires prior approval by the city engineer.
(D) All construction plans for grading and drainage, streets, water, sewer and storm drains shall be prepared per the standards set forth in these standards and Standard Details.
(E) If any plan submitted is not in compliance with these standards, or has in the plan reviewer’s opinion excessive corrections, the review may not continue and will be returned to the owner. Any plan submitted for review, even if discontinued, will be counted as a plan review submittal.
(G) Two (2) sets of drainage reports, grading and drainage, paving and storm drain plans, Storm Water Pollution Prevention Plan (“SWPPP”), and 6 sets of commercial and all other development plans with off-site improvements along perimeter streets are required for each submittal to the city’s development services department. Plan construction documents shall also be submitted in PDF electronics file format. The corresponding number of sets of plans and city redlines are required for all subsequent submittals.
(H) When final plans are submitted for approval signatures, a CD of the electronic CAD files of the construction plan sheets shall also be submitted per § 10-1-5(C). Each sheet file shall not contain any X-reference files which shall be “inserted” into the drawing file.
(I) Submittals of water and sewer plans shall be made directly to the utility companies and there must be verification by the developer of submittal requirements with each respective utility company.
(Ord. passed - - )