(A) Above ground utilities. Unless pre-empted and allowed by state law, the above ground erection or alteration of pipes, poles, wires and similar installations necessary to distribute public utilities shall require approval of an administrative use permit ("AUP"). Proposed utility substations shall be screened with a minimum 8 foot high decorative masonry wall.
(B) Below ground utilities. The installation of underground utilities shall be subject to Apache Junction City Code, Vol. II, Chapter 10, Engineering Design Guidelines and Policies.
(Ord. 1402, passed 5-6-2014)