(a) Filing of application. Within six months after approval of the concept plan, with or without conditions or revisions, the developer may file an application for approval of a sketch plan under § 17-3-201 or a preliminary plan under § 17-4-201. The application shall incorporate the provisions of the approved concept plan.
(b) Final plan or site development plan. The developer may omit submittal of an application for approval of a sketch plan or preliminary plan and may instead proceed with an application for approval of a final plan or site development plan in accordance with this article, without the need for a modification.
(c) Community meeting. Within 45 days after the submission of a final plan or site development plan, the developer shall hold a community meeting in accordance with § 17-2-107(c) and (d), but without reference to the limitations contained in § 17-2-107(a). The previous concept plan community meeting shall serve as the required pre-submission community meeting.
(Bill No. 64-20)