(a) Notification by developer. A developer shall notify the Department at least 48 hours before commencing work and on completion of any work in conjunction with the stormwater management plan.
(b) Inspections by the County. The Department shall make and document regular inspections, at a minimum, at each stage of construction and shall include the information specified in COMAR 26.17.02.10 and listed in the County Procedures Manual.
(c) Violations. When any violation is observed, the Department shall provide to the developer and to any onsite personnel written notice describing the nature of the violation and the required corrective action. The developer may not proceed with work until the Department inspects and approves the work previously completed.
(Bill No. 58-10; Bill No. 74-11)