(a) A certificate of occupancy shall be applied for and be approved by the I-1 District Board of Review before any building permit is issued for the construction or change in use of a building or use of land in the I-1 District.
(b) An application for a certificate of occupancy for a building and/or land use in the I-1 District shall be accompanied by the following:
(1) A plot plan of land or parcel of land to be used, showing dimensions, location of all existing and proposed buildings, storage areas, utilities, driveways, off-street parking areas, topography, abutting streets, railroads, highways, loading and unloading areas, signs and advertising structures, landscaping, drainage and watercourses, and other topographic features within 200 lineal feet of the parcel lines.
(2) Architectural plans for all proposed buildings, walls, fences, driveways, signs and other permanent structures.
(3) A description of the proposed business operation in sufficient detail to fully describe the nature and extent of the proposed use of each parcel included therein.
(4) Plans or reports describing proposed treatment of any excess traffic conditions, noise, odors, glare, pollution, etc. and the treatment and handling of hazardous gases, liquids or other material.
(5) Plans or reports showing proposed treatment and disposal of sewage and industrial waste.
(6) Description of any fuel to be used, including engineering plans for the control of any pollutants which may be generated therefrom.
(7) Any additional data which may be required by the I-1 District Board of Review to ascertain conformance with requirements of this district.
(8) All pollution control equipment must be fully operative before any production may be started.
(c) A certificate of occupancy for any building and/or land use in the I-1 District must be revoked by the I-1 District Board of Review if, after hearing, the Board of Review finds that the holder of such certificate has failed to comply with the requirements of this district.
(Ord. 20-13. Passed 3-23-20.)