§ 151.12 BOND REQUIREMENT.
   When in the opinion of the Building Commissioner and the Village Engineer, the termination before completion of a proposed excavation or fill operation would create an actual or potential hazard to the public, the Building Commissioner, prior to issuing the permit, shall require a bond in an amount as determined by the Commissioner and Engineer sufficient to cover the estimated cost of restoration of any affected land or to cover the cost of performance of the operations under such permit, whichever is greater.
('69 Code, § 154.12) (Ord. C-474, passed 1-8-79)
§ 151.13 FEE SCHEDULE.
   (A)   Before issuing a permit, the Building Commissioner or his designee shall collect a fee, the amount of which shall be $20 for the first 100 cubic yards (or fraction thereof) plus $10 for each 1,000 cubic yards (or fraction thereof) in excess of 100 cubic yards of earth or other materials moved, except that no fee shall be collected for work performed by any public agency.
   (B)   Before accepting a request for a waiver or modification, or application for a permit, pursuant to § 151.07 or § 151.08, the Building Commissioner or his designee shall collect from the person making such request or application a deposit of $100 to be applied to the charges of the Village Engineer for the engineering services provided pursuant to such sections; and no waiver or modification shall be given, or permit issued, until all charges of the Village Engineer have been paid by the person making the request or application. Should the charges of the Village Engineer be less than $100, the unused portion of the deposit shall be returned to the person who made such deposit.
('69 Code, § 154.13) (Ord. C-474, passed 1-8-79)
§ 151.14 PERMIT EXPIRATION.
   Excavation and fill permits shall be valid for one year. However, any permit may be renewed without cost for two additional one year periods by the Building Commissioner with the approval of the Village Engineer.
('69 Code, § 154.14) (Ord. C-474, passed 1-8-79)
§ 151.15 NOTIFICATION BY PERMIT HOLDER.
   The person to whom a permit is issued shall notify the Building Commissioner:
   (A)   Of the time of commencement of operations under such permit, 48 hours in advance of such time where excavation will enter a public right-of-way, and in all other instances 24 hours in advance of such time;
   (B)   Immediately of any delay in the time of commencement of which notification has been given as provided in division (A);
   (C)   When the operation is completed;
   (D)   Prior to commencement of operations, of the locations of any borrow sites or any disposal sites for excess materials.
('69 Code, § 154.15) (Ord. C-474, passed 1-8-79) Penalty, see § 151.99
§ 151.16 SUSPENSION OF OPERATIONS.
   The Building Commissioner shall order operations under a permit for excavation or fill suspended whenever he determines, with the concurrence of the Village Engineer, that such operations are endangering the public health or safety.
Such suspensions shall remain in effect until the condition or conditions causing same are successfully remedied to the satisfaction of the Commissioner and Engineer. The Building Commissioner, with the concurrence of the Village Engineer, shall also have the authority to order stopped any operations contrary to the terms and conditions of a permit issued under this chapter. Such stoppage shall remain in effect until the operations are remedied to be in conformance with this chapter.
('69 Code, § 154.16) (Ord. C-474, passed 1-8-79)