§ 50.31 INSPECTION OF CONNECTIONS.
   Not less than 12 hours previous to making a sewer connection the sewer tapper shall notify the Building Commissioner as to the time when the work will be ready for inspection. The sewer tapper shall keep the work uncovered, free, and clear until it is inspected and approved by the Inspector.
('69 Code, § 50.11) (Ord. 138, passed 4-15-56) Penalty, see § 50.99