(a) All development sites whose land disturbance is one acre or more require a Storm Water Pollution Prevention Plan to be submitted to the Stark Soil and Water Conservation District, 2650 Richville Dr. SE, Ste. 103, Massillon OH 44646.
(i) Include an approved copy of the SWP3 plan with construction plans and/or with the Storm Water Management Report to the City. The SWP3 plan must be approved prior to the start of any soil disturbing activities and before the Storm Water Management Report can be approved.
(ii) Calculations for the water quality and erosion control measures required for the SWP3 plan shall be included as a section in the Storm Water Management Report.
(iii) Soil erosion and sediment control practices used to satisfy these standards shall meet the standards and specifications in the current edition of the Ohio Rainwater and Land Development manual, NRCS Field Office Technical Guide for Stark County or the Ohio EPA, whichever is most stringent.
(b) A Notice of Intent (NOI) for requesting coverage under an Ohio EPA General Permit to discharge construction site stormwater is required to be filed with the OEPA at least 45 days prior to the start of construction, per the Ohio Water Pollution Control Act - 33 U.S.C. 1251.