§ 20.19.050 PERMIT REVIEW AND INSPECTION REQUIREMENTS.
   (A)   Prior to submitting an application, the applicant shall:
      (1)   Verify to the applicant’s reasonable satisfaction through the use of standard engineering evaluation techniques that the support structure for the small residential rooftop solar energy system is stable and adequate to transfer all wind, seismic, and dead and live loads associated with the system to the building foundation; and
      (2)   At the applicant’s cost, verify to the applicant’s reasonable satisfaction using standard electrical inspection techniques that the existing electrical system including existing line, load, ground and bonding wiring as well as main panel and subpanel sizes are adequately sized, based on the existing electrical system’s current use, to carry all new photovoltaic electrical loads.
   (B)   For a small residential rooftop solar energy system eligible for expedited review, only one inspection shall be required, which shall be done in a timely manner and may include a consolidated inspection by the building official and fire chief. If a small residential rooftop solar energy system fails inspection, a subsequent inspection is authorized; however the subsequent inspection need not conform to the requirements of this division (B).
   (C)   An application that satisfies the information requirements in the checklist, as determined by the Building Official, shall be deemed complete. Upon receipt of an incomplete application, the Building Official shall issue a written correction notice detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.
   (D)   Upon confirmation by the Building Official of the application and supporting documentation being complete and meeting the requirements of the checklist, the Building Official shall administratively approve the application and issue all required permits or authorizations. Such approval does not authorize an applicant to connect the small residential rooftop energy system to the local utility provider’s electricity grid. The applicant is responsible for obtaining such approval or permission from the local utility provider.
(Ord. 4676, passed 9-28-15)