§ 13.48.120 CONTENTS OF NOTICE.
   The notice given by the Director of Public Works to provide the required underground facilities shall particularly specify what work is required to be done, and shall state that if the work is not completed within 30 days after receipt of such notice, the Director of Public Works will provide such required underground facilities, in which case the cost and expense thereof will be assessed against the property benefited and become a lien upon such property.
('86 Code, § 13.48.120) (Ord. 3401, passed - - )