If the work is unsatisfactory or is not being prosecuted diligently in the opinion of the Director of Public Works, the permittee shall be notified in writing, and shall be required to conform within 24 hours after service of such notice. If such notice is not complied with, the Director of Public Works may cause the work to be completed, and the cost of the work to complete the excavation, fill or backfill shall be assessed against the permittee.
('86 Code, § 13.20.130) (Ord. 3002, passed - - ) Penalty, see § 1.12.010