§ 153.149 SUBMITTAL REQUIREMENTS.
   The following information is required.
   (A)   The names of project applicant;
   (B)   The name of the project owner;
   (C)   The legal description and address of the project;
   (D)   A description of the project including number, type, name plate generating capacity, tower height, rotor diameter and total height of all wind turbines and means of interconnecting with the electrical grid, if applicable;
   (E)   Site layout, including the location of property lines, wind turbines, electrical wires, interconnection points with the electrical grid and all related accessory structures. The site layout shall include distances and be drawn to scale;
   (F)   Engineer’s state certification and project design specifications; and
   (G)   Documentation of land ownership or legal control of the property.
(Prior Code, § 12-229) (Ord. 05-2010, passed 6-15-2010; Ord. 10-2010, passed 11-16-2010)