The Director of Public Works shall conduct inspections to ensure compliance with this Chapter.
(a) Inspection. The following inspections may be performed by the Director of Public Works:
(1) Pre-Site Inspection. To determine the potential for erosion resulting from the proposed project;
(2) Operation Progress Inspections. To determine ongoing compliance and the necessity of additional erosion control measures; and
(3) Final Inspection. To determine compliance with approved plans and specifications.
(b) Notification. The permittee shall notify the Director of Public Works at least twenty-four (24) hours prior to the start of authorized work on the project, and also nine (9) business hours prior to any inspection requested by permittee or permittee's authorized agent.
(c) Right of Entry. The filing of an application for a development permit constitutes a grant of permission for the City to enter the permit area for the purpose of administering this chapter from the date of the application to the termination of the erosion control maintenance period.