A. Effect. Approval of a development application in accordance with this Ordinance authorizes only the particular use, plan for development, or other specific activity approved.
B. Permit Prerequisite. In the event a permit or development approval is a prerequisite to another permit or development approval (e.g., administrative adjustment or variance approval prior to a site plan approval), development may not take place until all prerequisite approvals are obtained. Approval of one development application does not guarantee approval of any subsequent development application.
C. Transfer.
1. Except when otherwise specified, development approvals may be transferred from one owner to another, provided the land, structure, or use type continues to be used for the same purpose for which the approval was granted.
2. The terms, requirements, and conditions of the approval shall continue to apply to all subsequent owners or interests.
(Ord. 2020-36, passed 12-2-2019)
2.3.11. Continuance, Postponement, and Withdrawal
An applicant may request that a review authority's consideration of a development application be continued, postponed, or withdrawn by submitting a written request to the appropriate review authority.
A. Procedure for Applications Subject to a Public Hearing.
1. In cases where an applicant seeks a continuance or postponement of an application subject to a public hearing, but public notification of the hearing has not yet been provided, the Planning Director shall consider and decide the request.
2. If public notification of the pending public hearing has been provided in accordance with this Ordinance, the request for continuance or postponement shall be placed on the public hearing agenda and be considered by the review authority. Additional public notification may be required.
3. A request for continuance or postponement may be approved in cases where the applicant needs additional time to prepare evidence, secure approval from outside agencies, bring the application into closer alignment with the Town's adopted policy guidance or the requirements of this Ordinance, or for good cause, as determined by the review authority.
B. Withdrawal.
1. An applicant may withdraw an application at any time.
2. If an applicant withdraws an application for the same land after public notification two times within a single calendar year, the same application may not be resubmitted for a period of one year from the date of the second withdrawal.
3. Application fees for withdrawn applications shall not be refunded.
(Ord. 2020-36, passed 12-2-2019)