9.68.100: LAPSE OF PERMITS/PERMIT EXPIRATION:
   A.   Expiration: A site plan and design review permit approval shall expire three (3) years from the date the permit is approved unless it is otherwise conditioned or unless prior to the expiration of the three (3) years the following have occurred:
      1.   A building permit is issued and substantial construction is diligently pursued toward completion of the project which was the subject of the site plan and design review permit application. After construction is commenced, if work is discontinued for a period of two (2) years, the site plan and design review permit requires review and reauthorization by the commission; or
      2.   A certificate of occupancy is issued for the structure which was the subject of the site plan and design review permit application.
   B.   Phased Projects: Projects may be built in phases if so approved by the commission or director pursuant to section 9.68.090, "Minor Modification Of Previously Approved Site Plan And Design Review", of this chapter. (Ord. 243, 10-15-2013)