A. Expiration: A conditional use permit approval shall expire three (3) years from the date the permit is approved unless it is otherwise conditioned or unless prior to the expiration of the three (3) years the following have occurred:
1. A building permit is issued and substantial construction is diligently pursued toward completion of the project which was the subject of the conditional use permit application. After construction is commenced, if work is discontinued for a period of two (2) years, the conditional use permit shall require review and reauthorization by the commission; or
2. A certificate of occupancy is issued for the structure which was the subject of the conditional use permit application.
B. Phased Projects: Projects may be built in phases if so approved by the commission or director pursuant to section 9.63.090, "Minor Modifications Of Previously Approved Conditional Use Permit", of this chapter. (Ord. 243, 10-15-2013)