A. Prior to starting the project, every applicant shall submit a properly completed waste management and diversion plan (WMP) to the WMP compliance official on a form prescribed by the city, as a portion of the building and/or demolition permit process.
B. The WMP compliance official is authorized to create guidelines setting forth the information to be included in a WMP, as well as the form thereof. At a minimum, the WMP shall delineate all of the following:
1. The C&D waste to be generated by the covered project.
2. The square footage of the proposed project.
3. The estimated weight of the C&D waste to be generated by the covered project, listed by material types.
4. The estimated weight of the C&D waste to be generated by the covered project to be diverted, listed by material types.
5. The facility or facilities to which C&D waste will be taken, listed by material types.
6. The estimated weight of C&D materials that will be landfilled.
7. Project proposed diversion method.
C. Pursuant to Yucaipa Municipal Code Chapter 8.28, only the city’s franchise waste hauler is authorized to provide roll-off bins and bin service. (Ord. 333 § 1, 2014)