4.20.117.1   Monthly progress reports.
During the construction, installation, upgrade or rebuild phases, the franchisee shall submit a monthly progress report (due on the tenth day of each calendar month until this phase is completed) which describes the contractor’s progress during the previous month. At a minimum the report shall indicate:
   4.20.117.1.1.   Dates of actions and milestones achieved;
   4.20.117.1.2.   Schedule extensions requested/received; and
   4.20.117.1.3.   Problems encountered and their resolution. (Ord. 205 § 3, 2001)