4.20.114.6   Delay in system construction.
   4.20.114.6.1.   Any delay in the cable system construction or reconstruction beyond the times specified in the plan timetable due to causes or events within the control of the franchisee, its agents or contractors shall require notification to and consent by the city. Any such delay beyond the terms of the construction timetable, unless approved by the city, will be considered a violation of the franchise for which the provisions of the ordinance codified in this title regarding assessing liquidated damages shall apply.
   4.20.114.6.2.   The city shall extend the period within which the franchisee is required to complete such construction or reconstruction by the period of any delay occasioned by any cause or event not within the franchisee's control, provided that the franchisee gives city notice of, and an explanation for, the occurrence of such delay within thirty (30) days after becoming aware of it.
   4.20.114.6.3.   Nothing in this section shall prevent a franchisee from constructing or reconstructing the cable system earlier than planned. (Ord. 205 § 3, 2001)