938.07 AS-BUILT PLANS, COMPLETION CERTIFICATE, AND FINAL INSPECTION.
   (a)   The developer shall be responsible for providing as-built plans of all SWM BMPs included in the approved SWM Site Plan. The as-built plans and an explanation of any discrepancies with the construction plans shall be submitted to the Municipality.
   (b)   The as-built submission shall include a certification of completion signed by a qualified person verifying that all permanent SWM BMPs have been constructed according to the approved plans and specifications. The latitude and longitude coordinates for all permanent SWM BMPs must also be submitted, at the central location of the BMPs. If any licensed qualified person contributed to the construction plans, then a licensed qualified person must sign the completion certificate.
   (c)   After receipt of the completion certification by the Municipality, the Municipality may conduct a final inspection to verify compliance with, and accuracy of, the as-built plans.
   (d)   The financial guarantee, as discussed under Section 940.03, shall not be released by the Municipality until the items in this Section are completed.
(Ord. 45-2022. Passed 8-16-22.)