931.12 PUBLIC NOTICE OF SIGNIFICANT VIOLATORS.
   The City of York shall annually provide public notification in a newspaper of general circulation that provides meaningful public notice within the jurisdiction(s) served by the POTW of Industrial Users which, at any time during the previous twelve months, were in significant noncompliance with applicable pretreatment standards and requirements. For the purposes of this provision, a Significant Industrial User (or any Industrial User that violates paragraphs (c), (d), or (h) of this section) is in significant noncompliance if its violation meets one or more of the following criteria:
    (a)   Chronic violations of wastewater discharge limits, defined here as those in which sixty-six percent (66%) or more of all of the measurements taken for the same pollutant parameter during a six-month period exceed (by any magnitude) a numeric pretreatment standard or requirement, including instantaneous limits, as defined by 40 CFR 403.3(l).
   (b)   Technical Review Criteria (TRC) violations, defined here as those in which thirty-three percent (33%) or more of all of the measurements taken for the same pollutant parameter during a six-month period equal or exceed the product of the numeric pretreatment standard or requirement including instantaneous limits, as defined by 40 CFR 403.3(l) multiplied by the applicable TRC. There are two groups of TRC:
 
Group I for BOD, TSS, fats, oil, and grease
TRC = 1.4
Group II for all other pollutants except pH   
TRC = 1.2
 
   (c)   Any other violation of a pretreatment standard or requirement as defined by 40 CFR 403.3(l) (daily maximum, long-term average, instantaneous limit, or narrative standard) that the POTW determines has caused, alone or in combination with other discharges, interference or pass through (including endangering the health of POTW personnel or the general public).
   (d)   Any discharge of a pollutant that has caused imminent endangerment to human health, welfare or to the environment or has resulted in the POTW's exercise of its emergency authority to halt or prevent such a discharge.
   (e)   Failure to meet, within ninety (90) days after the schedule date, a compliance schedule milestone contained in a local control mechanism or enforcement order for starting construction, completing construction, or attaining final compliance.
   (f)   Failure to provide, within thirty (30) days after the due date, required reports such as baseline monitoring reports, ninety (90)-day compliance reports, periodic self-monitoring reports, reports on best management practices, and reports on compliance with compliance schedules.
   (g)   Failure to accurately report noncompliance.
   (h)   Any other violation or group of violations, which may include a violation of Best Management Practices, which the POTW determines will adversely affect the operation or implementation of the local pretreatment program.
      (Ord. 16-2010. Passed 5-4-10.)