Upon receipt of an application for a building permit for work to be done in the historic district, or application for work to be done in the historic district that may not require a building permit but does require a Certificate of Appropriateness (see 1731.07(a)), the Building Official shall act in accordance with the procedures presently being followed in that office except as those procedures are necessarily modified by the following requirements:
(a) He shall forward to the office of the Board of Historic Architectural Review a copy of the application for a building permit and/or Certificate of Appropriateness for any work which is regulated by the provisions of this article together with a copy of the plot plan for the building plans and specifications filed by the applicant.
(b) He shall maintain in his office a record of all such applications and of his handling and final disposition of the same, which shall be in addition to an appropriate cross reference to his other records.
(c) He shall require applicants to submit a sufficient number of additional copies of material required to be attached to an application for a building permit or Certificate of Appropriateness to permit compliance with the foregoing.
(Res. 81-2014. Passed 9-2-14.)