(a) It is the responsibility of the permittee to notify the York City Engineer forty-eight hours in advance of beginning construction of storm water management facilities. The York City Engineer or his designee shall have the right to inspect all phases of development of the site including, but not limited to:
(1) Completion of preliminary site preparation including stripping of vegetation, stockpiling of topsoil, and construction of temporary storm water management and erosion control facilities.
(2) Completion of rough grading, but prior to placing top soil, permanent drainage or other site development improvements and ground covers.
(3) During construction of the permanent storm water facilities at such times as specified by the York City Engineer.
(4) Upon completion of permanent storm water management facilities, including established ground covers and plantings.
(5) Upon completion of any final grading, vegetative control measures or other site restoration work done in accordance with the approved plan.
(b) Any portion of the work which does not comply with the approved plan shall be promptly corrected by the developer. No work may proceed on any subsequent phase of the storm water management plan, the subdivision or land development or building construction until the required corrections have been made.
(c) Upon completion, the owner's/developer's engineer shall certify in writing to the York City Engineer all aspects of the storm water management plan have been constructed in accordance with the approved plans.
(d) If at any stage of the work, the York City Engineer determines that the soil or other conditions are not as stated or shown in the approved application, he may refuse to approve further work and may revoke existing approval until a revised plan is submitted and approved.
(Ord. 13-1981 §1. Passed 5-20-81.)