6-7-4: ADMINISTRATION:
   A.   Designation Of Floodplain Administrator: The town engineer is hereby appointed the floodplain administrator to administer and implement the provisions of this chapter and other appropriate sections of 44 CFR (national flood insurance program regulations) pertaining to floodplain management.
   B.   Duties And Responsibilities Of The Floodplain Administrator: Duties and responsibilities of the floodplain administrator shall include, but not be limited to, the following:
      1.   Floodplain administrator will supply the town planner with originals of all records pertaining to this chapter. Town planner shall serve as official custodian of all records pertaining to the provisions of this chapter. Town planner shall maintain and hold open for public inspection all records pertaining to the provisions of this chapter.
      2.   Review permit applications to determine whether a proposed building site, including the placement of manufactured homes, will be reasonably safe from flooding.
      3.   Review, approve, or deny all applications for development permits required by adoption of this chapter.
      4.   Review permits for proposed development to assure that all necessary permits have been obtained from those federal, state, or local government agencies (including section 404 of the federal water pollution control act amendments of 1972, 33 USC 1334) from which prior approval is required.
      5.   Where interpretation is needed as to the exact location of the boundaries of the areas of special flood hazard (for example, where there appears to be a conflict between a mapped boundary and actual field conditions) the floodplain administrator shall make the necessary interpretation.
      6.   Notify, in riverine situations, adjacent communities and the state coordinating agency which is Colorado water conservation board, prior to any alteration or relocation of a watercourse, and submit evidence of such notification to the federal emergency management agency.
      7.   Assure that the flood carrying capacity within the altered or relocated portion of any watercourse is maintained.
      8.   When base flood elevation data has not been provided in accordance with subsection 6-7-3B of this chapter, the floodplain administrator shall obtain, review, and reasonably utilize any base flood elevation data and floodway data available from a federal, state, or other source, in order to administer the provisions of section 6-7-5 of this chapter.
      9.   When regulatory floodway has not been designated, the floodplain administrator must require that no new construction, substantial improvements, or other development (including fill) shall be permitted within zones A1-30 and AE on the community's FIRM, unless it is demonstrated that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood more than one foot (1') at any point within the community.
      10.   Under the provisions of 44 CFR chapter 1, section 65.12, of the national flood insurance program regulations, a community may approve certain development in zones A1-30, AE, AH, on the community's FIRM which increases the water surface elevation of the base flood by more than one foot (1'), provided that the community first applies for conditional FIRM revision through FEMA (conditional letter of map revision).
   C.   Permit Procedures:
      1.   Application for a floodplain development permit shall be presented to the floodplain administrator on forms furnished by him/her and may include, but not be limited to, plans in duplicate drawn to scale showing the location, dimensions, and elevation of the proposed landscape alterations, existing and proposed structures, including the placement of manufactured homes, and the location of the foregoing in relation to areas of special flood hazard. Additionally, the following information is required:
         a.   Elevation (in relation to mean sea level) of the lowest floor (including basement) of all new and substantially improved structures;
         b.   Elevation (in relation to mean sea level) to which any nonresidential structure shall be floodproofed;
         c.   A certificate from a registered professional engineer or architect that the nonresidential floodproofed structure shall meet the floodproofing criteria of subsection 6-7-5B2 of this chapter;
         d.   Description of the extent to which any watercourse or natural drainage will be altered or relocated as a result of proposed development;
         e.   Maintain a record of all such information in accordance with subsection B1 of this section.
      2.   Approval or denial of a development permit by the floodplain administrator shall be based on all of the provisions of this chapter and the following relevant factors:
         a.   The danger to life and property due to flooding or erosion damage;
         b.   The susceptibility of the proposed facility and its contents to flood damage and the effect of such damage on the individual owner;
         c.   The danger that materials may be swept onto other lands to the injury of others;
         d.   The compatibility of the proposed use with existing and anticipated development;
         e.   The safety of access to the property in times of flood for ordinary and emergency vehicles;
         f.   The costs of providing governmental services during and after flood conditions including maintenance and repair of streets and bridges, and public utilities and facilities such as sewer, gas, electrical and water systems;
         g.   The expected heights, velocity, duration, rate of rise and sediment transport of the floodwaters and the effects of wave action, if applicable, expected at the site;
         h.   The necessity to the facility of a waterfront location, where applicable;
         i.   The availability of alternative locations, not subject to flooding or erosion damage, for the proposed use;
         j.   The relationship of the proposed use to the comprehensive plan for that area.
   D.   Variance Procedures:
      1.   Appeal Board To Hear Requests: The appeal board as established by the community shall hear and render judgment on requests for variances from the requirements of this chapter.
      2.   Appeal Board To Hear Appeals: The appeal board shall hear and render judgment on an appeal only when it is alleged there is an error in any requirement, decision, or determination made by the floodplain administrator in the enforcement or administration of this chapter.
      3.   Aggrieved By Decision Of Appeal Board: Any person or persons aggrieved by the decision of the appeal board may appeal such decision in the courts of competent jurisdiction.
      4.   Records; Reports: The floodplain administrator shall maintain a record of all actions involving an appeal and shall report variances to the federal emergency management agency upon request.
      5.   Historic Structures: Variances may be issued for the reconstruction, rehabilitation, or restoration of structures listed on the National Register of Historic Places, or the State Inventory of Historic Places without regard to the procedures set forth in the remainder of this chapter.
      6.   Lot Size: Variances may be issued for new construction and substantial improvements to be erected on a lot of one-half (1/2) acre or less in size contiguous to and surrounded by lots with existing structures constructed below the base flood level, providing the relevant factors in subsection C2 of this section have been fully considered. As the lot size increases beyond the one-half (1/2) acre, the technical justifications required for issuing the variance increase.
      7.   Conditions Of Variance: Upon consideration of the factors noted above and the intent of this chapter, the appeal board may attach such conditions to the granting of variances as it deems necessary to further the purpose and objectives of this chapter (subsection 6-7-1C of this chapter).
      8.   Within Designated Floodways: Variances shall not be issued within any designated floodway if any increase in flood levels during the base flood discharge would result.
      9.   Repair Or Rehabilitation Of Historic Structure: Variances may be issued for the repair or rehabilitation of historic structures upon a determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and the variance is the minimum necessary to preserve the historic character and design of the structure.
      10.   Prerequisites For Granting Variances:
         a.   Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.
         b.   Variances shall only be issued upon:
            (1)   Showing good and sufficient cause;
            (2)   A determination that failure to grant the variance would result in exceptional hardship to the applicant; and
            (3)   A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, create nuisances, cause fraud on or victimization of the public, or conflict with existing local laws or ordinances.
         c.   Any applicant to whom a variance is granted shall be given written notice that the structure will be permitted to be built with the lowest floor elevation below the base flood elevation, and that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation.
      11.   Functionally Dependent Use: Variances may be issued by a community for new construction and substantial improvements and for other development necessary for the conduct of a functionally dependent use, provided that:
         a.   The criteria outlined in subsections D1 through D9 of this section are met, and
         b.   The structure or other development is protected by methods that minimize flood damages during the base flood and create no additional threats to public safety. (Ord. 424, Series of 2009)
   E.   Penalties: No structure or land shall hereafter be constructed, located, extended, converted, or altered without full compliance with the terms of this chapter and other applicable regulations. Violations of the provisions of this chapter by failure to comply with any of its requirements (including violations of conditions and safeguards established in connection with conditions) shall constitute a misdemeanor. Any person who violates this chapter shall upon conviction thereof be punished as provided in subsection 1-4-1C of this code. Nothing herein shall prevent the town from taking such other lawful action as is necessary to prevent or remedy any violation. (Ord. 473, Series of 2013)