(A)
No building permits will be issued until the developer has installed sanitary sewer and water service, in accordance with the city’s standards, and has completed construction of storm drainage as determined necessary by the developer’s engineer and agreed to by the City Engineer, as well as completed grading the street past the property upon which a building is to be constructed.
(B) Before final approval of a plat is given, the developer must provide a bond with corporate surety or other assurances satisfactory to the city, which will assure the city that the construction of water, sanitary sewer, storm sewer, road construction and other necessary improvements as approved by the City Council will be completed within three years. No extension of time beyond this three-year period unless the bond remains valid and enforceable throughout such extended period.
(Prior Code, § 15.05.10) (Ord. 1056, passed 8-7-2023)