§ 52.039 WHEN PUBLIC SEWER AVAILABLE, CONNECTION REQUIRED.
   At such time as a public sewer becomes available to a property served by a private wastewater disposal system, a direct connection shall be made to the public sewer within 30 days in compliance with this chapter, and within 30 days any septic tanks, cesspools and similar private wastewater disposal systems shall be cleaned of sludge. The bottom shall be broken to permit drainage and the tank or pit filled with suitable material.
(Ord. 117, passed 2-26-86)