(A) The Commission’s staff shall determine if the petitioner’s submission is complete.
(1) If it is complete, written notices shall be sent to the petitioner, the petitioner’s representatives, the Technical Advisory Committee, and the staff, scheduling a required review meeting to be held at a date and time as determined by the Zoning Administrator.
(2) If the submission is found to be incomplete, the Technical Advisory Committee shall provide the petitioner feedback verbally, or in writing, during the TAC meeting.
(B) At the required review meeting, the staff and Technical Advisory Committee will have an opportunity to recommend revisions to the draft or preliminary plan submission and discuss them with the petitioner and petitioner’s representatives. Technical Advisory Committee members may provide written comments to the administrative official instead of being present.
(Ord. 23, § 3.80.60, passed 3-19-1997; Am. Ord. 23-A, passed 2-8-2022)