§ 155.047 APPROVAL OF ENGINEERING PLANS.
   (A)   Submission procedure and requirements. Before approval of the primary plat, the applicant, if he or she wishes to proceed with the subdivision, shall submit ten copies of the engineering plans prepared by a civil engineer or surveyor registered in this state pursuant to § 155.031 of this code, and shall file with the Administrator a request to start work on any improvements.
   (B)   Review process.  
      (1)   Two copies of the plans shall be referred to the County Highway Department, the County Health Department or the common water or sanitary sewer utility, the Natural Resources Conservation Service, the Town Engineer, and one copy for the Administrator. Upon receipt of approved engineering plans the applicant may proceed with the installation of improvements provided there is approved surety in place for the cost of the improvements. In no event shall secondary approval be given prior to approval of the engineering plans.
      (2)   Upon receipt of the required documents the Town Engineer shall examine the plans and submit a written report to the Commission, taking either no exception or exception to the plans, profiles, and specifications. In the event the Town Engineer does not accept the plans, profiles, and specifications, he or she shall state the reasons for disapproval in writing to the Commission, and his or her report shall be recorded by the Commission.
   (C)   Installation of improvements. The installation of improvements shall be inspected by the town and any other agency having statutory or jurisdictional review authority. The inspections are required in all instances regardless of whether the work is performed before or after secondary approval. Failure to request inspection of work performed after the date of this chapter and before secondary approval where applicable may be cause for denial of secondary approval.
(Ord. 27, § 3.20.30, passed 4-16-1997)