1111.12 ACTION BY PLANNING AND ZONING COMMISSION.
   (a)    For a preliminary or final development plan, the Planning and Zoning
Commission shall either:
      (1)    Approve the development plan as submitted; or
      (2)    Approve the plan subject to specific conditions not included in the plan as submitted, such as, but not limited to, improvements in the setback layout, open space arrangement, on-site control of access to streets, or such features as fences, walls and plantings to further protect and improve the proposed and surrounding developments; or
      (3)    Deny the development plan when the application does not demonstrate that the required standards have been met.
   (b)    For a preliminary or final development plan, the Planning and Zoning Commission may also postpone the development plan for the next scheduled Planning and Zoning Commission meeting, demonstrating to the applicant an acceptable alternative plan.
   (c)    Failure of the Planning and Zoning Commission to act within sixty (60) days from the date the application was deemed complete, or an extended period as may be agreed upon, the applicant may deem the application denied.
(Ord. 2006-35. Passed 5-25-06.)