§ 1343.04 NEW CONSTRUCTION RESULTING IN TWO OR MORE PRINCIPAL BUILDINGS ON A LOT.
   If one or more new principal building(s) are constructed on a lot so as to result in a total of two or more principal buildings on the lot, with two or more different principal uses present on the lot, then the following additional requirements shall apply.
   (a)   The lot must meet the minimum lot area specified in the district, and shall not have non-conforming lot area. Where different dimensional requirements apply to different uses, the most restrictive requirement shall apply.
   (b)   Special exception approval shall be required. The applicant shall show that there is adequate access for emergency vehicles and equipment.
   (c)   Any new construction shall meet all applicable yard requirements. The total development of the lot shall meet all lot coverage requirements.
   (d)   The requirements of this section shall not apply with the CBD District.
   (e)   For a lot with two or more existing principal buildings, see § 1323.02(b).
(Ord. 5745, approved 4-16-1998)