§ 1311.881 START OF CONSTRUCTION.
   START OF CONSTRUCTION means for floodplain management purposes, substantial improvements and other proposed new development and means the date that the permit was issued; provided, the actual START OF CONSTRUCTION, repair, reconstruction, rehabilitation, addition, placement or other improvement was within 180 days after the date of the permit and shall be completed within 12 months after the date of issuance of the permit unless a time extension is granted, in writing, by the Floodplain Administrator. The actual START means either the first placement of permanent construction of a structure on a site, such as pouring of slab or footings, the installation of piles, the construction of columns or any work beyond the stage of excavation; or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading and filling; nor does it include the installation of streets or walkways; nor does it include excavation for a basement, footings, piers or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual START OF CONSTRUCTION means the first alteration of any wall, ceiling, floor or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
(Ord. 6253, approved 2-6-2014)