§ 56.151 FINAL INSPECTION AND ACCEPTANCE.
   (A)   Upon written notification by the permittee, the resident engineer or the person in charge that the construction has been completed, including the submission of all required reports, the WCDOT shall perform a final inspection. Prior to final approval and acceptance by the WCDOT, the permittee shall correct any deficiencies noted by the WCDOT and provide one set of electronic as-builts for the WCDOT records, if required by permit type.
   (B)   At such time as all work has been done to the complete satisfaction of the WCDOT and the maintenance guarantee provided, the performance guarantee shall be released.
   (C)   WCDOT may restrict final inspections for release of the performance or maintenance guarantee between May 1 and November 1.
(Ord. 20-231, passed 7-16-2020)