1387.01  PROGRESS INSPECTIONS.
   (a)   The developer shall notify the Inspector at least seventy-two hours prior to beginning any installation of public improvements in an approved plan.  While work is in progress, the developer shall notify the Inspector at least seventy-two hours prior to the time that the following required progress inspections are desired:
      (1)   Inspection of sub-grade of streets prior to laying of base;
      (2)   Inspection of base prior to final paving of streets; and
      (3)   Inspection on installation of water lines, sanitary sewer lines, storm sewers and drainage facilities before they are covered.
 
   (b)   The Inspector shall prepare a written report of all inspections in duplicate on forms provided by the Borough.  One copy shall be retained by the Borough and one copy shall be retained by the Borough Engineer.
(Ord. 2748.  Passed 11-17-86.)