(A) The establishment of common open spaces and construction of public or common recreational facilities shown on the recorded final development plan together with the construction of other nonresidential structures shall proceed substantially in accordance with the phasing program referred to in § 154.071(A)(2)(d), General Submission, herein.
(B) After general construction commences, the developer shall submit progress reports every six months to the Planning Commission who shall review all building permits issued and compare them to the overall development phasing program. If it is determined that the rate of construction of residential units or nonresidential structures substantially differs from the phasing program, they shall so notify the developer in writing.
(C) Thereafter, the Planning Commission may issue such orders to the developer as it sees fit, and upon continued violation of this section may suspend the developer from further construction of dwelling units or nonresidential structures until compliance is achieved.
(Ord. 101, passed 4-11-77)