1753.16 INSPECTIONS.
   (a)    Rough piping inspection shall be made after all new piping authorized by the permit has been installed, and before any such piping has been covered or concealed or any fixtures or gas appliances have been attached thereto. See Section 210 of the Standard Gas Code.
   (b)    Final piping inspection shall be made after all piping authorized by the permit has been installed and after all portions thereof which are to be concealed by plastering or otherwise have been so concealed, and before any fixtures or gas appliances have been attached thereto. This inspection shall include a pressure test.
   (c)    Final inspection shall be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes, to insure compliance with all the requirements of this Code and to assure that the installation and construction of the gas system is in accordance with approved plans.
   (d)    All tools, apparatus, labor and assistance necessary for the tests shall be furnished by the installer.
(Ord. 6424. Passed 11-29-77.)