(a) All material, both conducting and supporting shall have sufficient mechanical strength to adequately meet with the requirements as determined by the length of the span and climatic conditions of this area.
(b) Approved vertical clearances shall be provided and maintained under all cables and lines in accordance with the classification of the areas over which the aerial facilities pass, that is, public or private property, streets, railroads, etc.
(c) Adequate vertical and horizontal clearances shall be provided and maintained from all aerial and service line facilities of the power, light and telephone companies, and shall comply with their specifications as to clearances when attached to their supporting equipment or are within the proximity of their equipment.
(d) Approved grounding and lightning protection shall be provided for the system and at each service, as needed, in accordance with accepted practice for television transmission systems.
(e) All installation and design shall be in accordance with accepted good engineering practice.
(f) The approval of plans for the construction and installation of television transmission systems shall be in accordance with Section 909.06(a).
(Ord. 2077. Passed 9-8-53.)