§ 125.34 INSTALLATION OF IMPROVEMENTS.
   125.34(A)   Completion of required improvements. All improvements required from the developer as a condition to the approval of an application for a , including but not limited to water, , paving, drainage, signs, fire hydrants, and connected lighting, shall be installed and completed prior to the issuance of the first for a principal .
   125.34(B)   Water, and drainage improvements. Any water, or drainage improvements proposed or required to be constructed within the proposed road shall be installed and completed before acceptance of any proposed or required road improvements by the appropriate agency.
   125.34(C)   Paved access. Prior to the issuance of the first , the developer shall provide paved fire access to all existing and proposed vertical within the site. Said paved access shall be approved by the .
(Ord. 2010-21, passed 10-4-2010)