XIII.   JOB SITE GUIDELINES
   A.   Start of Construction
No lot clearing or placement of either sales and/or construction trailers, and portable toilets will be permitted until closing on the lot has occurred, all required governmental permits are obtained and formal written approval of the ARB has been granted.
   B.   Portable Toilets, Construction and Sales
Prior to commencing work, all temporary facilities must be placed on the job site and in a manner so as to least disturb other residents, other construction and the marketing of the community. Portable toilets shall be cleaned on a regular basis and shall not become noxious.
   C.   Construction Traffic
Parking of construction vehicles is prohibited on swales or grassy areas. Washing of vehicles on the streets is also prohibited. parking is prohibited on public .
   D.   Construction Hours
The construction working hours shall be from 6:00 a.m. to 7:30 p.m. Monday through Friday, Saturday 7:00 a.m. to 5:30 p.m., Sunday 12:00 p.m. to 5:00 p.m. except on certain holidays. Additional hours may be provided upon approval of the ARB.
   E.   Site Clean-Up
All construction sites must be maintained in a neat and orderly fashion. from construction work will be contained in a trash dumpster or removed from the job site on a routine basis. The Application is responsible for trash that blows off the site and shall retrieve such trash. There will not be stockpiling or dumping on streets or in the lakes, waterways or wetlands. removed by the Developer will be billed to the responsible . will use only the utilities provided on the immediate site on which they are working.
   F.   Construction Damage
Any damage to streets and curbs, drainage inlets, sidewalks, street lights, street markers, mail boxes, walls, etc., will be repaired by the at its sole cost and its expense. If said damage is not repaired by the , the Developer may repair said damage and bill same to .
   G.   Established Speed Limit
The established speed limit within the Estates of Swan Lake is 25 mph for construction vehicles, including light trucks and auto.
   H.   Construction Spillages
Operators of vehicles are required to clean up if spillage of a load occurs while within the Estates of Swan Lake. Clean-ups done by the at its sole cost and its expense. If said damage is not repaired by the , the Developer may repair said damage and bill same to .
   I.   Telephone (Cable TV Lines)
If any telephone, cable television, electrical, water, etc., lines are cut, it is the Participating ’s responsibility to report the accident to the Developer’s field representative. Costs incurred to repair such damages, if applicable, will be charged to the .
   J.   Construction Site Appearance
All personnel working in the Estates of Swan Lakes are to keep all areas in which they work free of discarded materials such as lunch bags and odd materials. Throwing objects out of cars and trucks is prohibited.
   K.   Loud Noise Levels
Loud radios or noise will not be allowed within the Estates of Swan Lake. This is distracting and discomforting to Property . Normal radio levels are acceptable. Do not mount speakers on vehicles or outside of homes under construction.
   L.   Vehicles and Equipment
The Developer is not responsible for any vehicle or its contents (trucks, vans, cars, etc.) left in the Estates of Swan Lake overnight equipment may be left on the site while needed, but must be kept on the street, unless prior permission has been granted.
   M.   Personnel
Only bona fide workers are allowed on the construction sites and are required to exit the property upon completion of their work. No children or family members of workers will be permitted on the construction sites. No alcoholic beverages are permitted on the property. Participating Builder personnel will not be permitted to bring pets on property.
   N.   Lake Restrictions
No hazardous or toxic substances, chemicals, pesticides, fertilizers or any other matter shall be dumped into any lake, wetland or canal which is within or abuts the properties or surface water management system of the properties. The use of pesticides, herbicides and fertilizers shall be prohibited on any wetlands or preservation areas.
   O.   Construction Inspection
Although the is responsible to comply with the conditions of the ARB approval, periodic inspections may be made by the ARB while construction is in progress to determine compliance with the approved architectural documents. However, the ARB is not specifically responsible to make such an inspection. The ARB is empowered to enforce its policy, as set forth in the Declaration and this manual, by any action, including an action in a court of law, to insure compliance.