32.07(A)
approved contracts.
32.07(A)(1) Termination. Contracts approved by the
may be terminated only by the
. If the
desires to terminate a
approved contract, the
may suspend the work under the contract until the
makes a final determination.
32.07(A)(2) Extensions. The
may extend a
approved contract for up to 90 days. The extension of any
approved contract for longer than 90 days shall be subject to prior approval by the
. In the event of an Emergency, the
may extend a
approved contract without
approval, subject to later ratification by the
.
32.07(A)(3) Renewals. When a contract is entered into by the
pursuant to
approval and provides for one or more renewals by affirmative action of the
, only the
may approve such renewals.
32.07(A)(4) Suspensions. The
may suspend a
approved contract for up to 90 days. Suspension of a
approved contract for longer than 90 days shall be subject to
approval.
32.07(B) City Manager approved contracts.
32.07(B)(1) Termination. Contracts that were not approved by the
may be terminated by the
.
32.07(B)(2) Extensions. The
is authorized to extend for up to 120 days any contract entered into by the
that was not approved by the
.
32.07(B)(3) Renewals. When a contract is entered into by the
pursuant to
approval and provides for one or more renewals by affirmative action of the
, the
is authorized to approve such renewals without
approval.
32.07(B)(4) Suspensions. Contracts that were not approved by the
may be suspended by the
.
(Ord. 2011-04, passed 5-16-2011; Am. Ord. 2023-07, passed 7-5-2023)