32.06(A) City Commission approved contracts.
32.06(A)(1) Beyond the Scope of
. Any
that materially expands or alters the scope of the work in a
approved contract shall be subject to prior approval by the
.
32.06(A)(2) Within the Scope of
. The
may approve a
provided that it does not materially expand or alter the scope of the work in a
approved contract. Any such
approved by the
shall be subject to ratification by the
as soon as practicable.
32.06(A)(3) Extension of Completion Dates. Any
that extends the original substantial or final completion date of a
approved contract shall be subject to prior approval by the
.
32.06(B)
approved contracts. The
is authorized to approve a
to a contract that was not approved by the
, provided that the
does not cause the total acquisition from the vendor to exceed the aggregate sum of $150,000 during the course of any
pursuant to Section 32.03(B).
(Ord. 2011-04, passed 5-16-2011; Am. Ord. 2023-07, passed 7-5-2023)