901.04 BARRICADES AND LIGHTS; RESTORATION TIME LIMIT.
   In the event any excavation or opening is not barricaded and lighted at any time, the Police Department or the Director of Engineering may cause such barricading and lighting to be done. Any expense in connection therewith for time, labor or material shall be charged to the deposit provided for in Section 901.03 and the City shall be reimbursed therefor.
   Every excavation or opening shall be repaired and the pavement or surface thereof restored to its previous condition within a period of one week from the commencement of such opening or excavation, unless the permittee has secured from the Director, in writing and for good and sufficient cause an extension of the permit issued. If such opening or excavation is not filled and completed within a period of one week, the Director may have such work performed and the cost thereof shall be charged to such deposit.
(Ord. 1988-258. Passed 5-18-89.)