§ 151.06 WPWD EROSION CONTROL INSPECTIONS.
   (A)   The WPWD erosion control inspector will inspect erosion and sediment control measures in conjunction with routine inspections. Inspections will ensure that proper placement and installation of erosion and sediment control measures are in place.
   (B)   The first inspection will occur at the time prior to the pushing of the pad and foundation installation. Standard items to be checked are: protection of adjacent lots, protection of inlets, grading/excavating and that stockpiles are stabilized. If BMPs are not installed in the correct location and/or not installed correctly, the inspection may be denied, a stop work order required or fees may be applied.
   (C)   It is anticipated that by the time the foundation inspection is requested, backfilling of the foundation will have been complete and all erosion and sediment control measures will have been installed. If the permittee fails to install the proper erosion and sediment control measure, this may result in the inspection being denied, a stop work order required or fees may be applied.
   (D)   For unique situations the erosion control inspector will be available to discuss erosion and sediment control measures for any lot and the sequencing for installation of BMPs.
(Prior Code, § 34-116) (Ord. 06-52, passed 11-13-2006; Ord. 15-03, passed 3-9-2015)