1176.03 PERMITTING AND APPLICATION.
   (a)   No alternative energy system shall be erected or installed in the City unless a permit has first been issued by the Chief Building Official and zoning certificate issued by the Zoning Officer.
   (b)   Written application for an alternative energy system shall be made to the Building Department. The application shall include:
      (1)   The address of the property, and the name, address and telephone number of the owner and occupant of the property.
      (2)   A site plan of the property showing the exact location of the proposed alternative energy system, all existing utility lines (specifically indicating overhead lines), setbacks, easements and all other structures on the premises.
      (3)   A description of the proposed alternative energy system, including information regarding its construction, method of assembly, installation and intended use as either a primary, ancillary or back-up power or emergency power source.
      (4)   Plans showing the specifications and elevations of the proposed system.
      (5)   A landscaping plan showing the size, quantity and types of landscaping materials to be used for screening.
      (6)   If the applicant is not the owner of the premises, the application shall include a statement by the owner giving the applicant written consent to install the system on the premises.
(Ord. 2011-12. Passed 3-15-11.)