§ 50.084 CONSTRUCTION GENERALLY.
   (A)   All work shall be inspected and approved by an authorized inspector of the village, at the expense of the applicant. Any work covered prior to the inspection shall be uncovered by the contractor and an opportunity provided to inspect the pipe.
   (B)   All material, pipe, bends, and equipment needed to properly install the building sewer and/or water service lateral must be on the site prior to the initiation of construction.
   (C)   Prior to initiating any work within any right-of-way, the contractor shall obtain from the proper authority the required permit for the excavation and shall comply with all the requirements of the issuing authority. This permit shall be shown to the inspector at the commencement of construction.
   (D)   All excavations for building sewer and water service lateral installations shall be adequately guarded with barricades and lights to protect the public from hazard.
   (E)   All construction must take place between 7:00 a.m. and 3:30 p.m., Monday through Friday. Construction performed on Saturday, Sunday, or holidays, if permitted, will necessitate additional inspection fees pursuant to §§ 50.120 through 50.124.
   (F)   The Village Engineer or his or her authorized agent shall approve the quality of all materials and workmanship and shall have the right to inspect the same at all times. Any inferior or defective material may be ordered from the job and shall be cause for a portion of a water service lateral or building sewer to be replaced and reinstalled.
   (G)   It shall be the property owner’s responsibility to properly situate, with respect to location and elevation, any new structure to which sanitary sewer service is to be provided by the village in order to ensure that the service desired can be obtained.
(Ord. 97-104, passed 2-3-1997) Penalty, see § 50.999