(A) Measures shall be taken to minimize erosion and its impacts during subdivision construction activity. Detailed erosion control plans shall be submitted with the improvement plans and shall indicate the techniques to be used both temporarily (during construction) and permanently, and include a schedule for implementing or installing same. All erosion control devices shall be in place at the start of construction and other measures implemented according to the approved time schedule.
(B) Erosion control plans shall be based upon controlling erosion on-site, with the object of eliminating or minimizing erosion or sedimentation impacts off-site. Techniques, devices, or measures used shall be as approved by the Village Engineer based on site conditions and the requirements of the Soil Conservation Service Handbook Water Management and Sediment Control for Urbanizing Areas.
(Ord. 96-106, passed 3-20-1996)